The contractors are working on their punch lists to complete their work. The roofers and plumbers are working on the roof penetrations and stacks for the kiln exhausts.
Shelf building continues in the classrooms. Here is one set in the Wheel 2 classroom.
We got 2 on the kilns on their tracks. Also fitted them with gaskets at the doors and mounted the control boxes. Still need to finish setting up the large gas kiln.
Trim work was completed on the marquee. Still need exterior painting and signage.
Welcome back to our tenants, the Somerville Police Department/East Somerville substation. They occupy the left hand storefront; hours are Monday through Friday, 8 am-4 pm, with evening hours on Tuesdays and Thursdays. Stop in and say hi to Capt. Fallon and his team.