February 25, 2011

Yesterday was another concrete day – new concrete poured in the main entry area and for the new 2nd floor balcony.   Now for a tour of the basement utility room: our hot water heater,the gas regulators, the main water … Continue reading

Posted in Uncategorized | Leave a comment

February 22, 2011

After our regular team meeting this morning, the Marquee Decorative Bracket Fabrication team met up with our architects and field supervisor to review the details for constructing the marquee. First Kent had built a life size model of the bracket. … Continue reading

Posted in Uncategorized | Leave a comment

February 20, 2011

Here’s a lot of new photos – great progress everywhere! The main hallway, 1st floor, looking to the rear of the building. The metal fabricated railings for the 2nd floor atrium were just delivered. Plastering has begun on the new … Continue reading

Posted in Uncategorized | 3 Comments

February 15, 2011

Work continues on the clerestory. Here’s an exterior view from up on the roof. Along with the new skylight that is waiting to be installed at the rear of the building. And here’s an inside view with the newly plastered … Continue reading

Posted in Uncategorized | 1 Comment

February 8, 2011

Focus this week is on the 2nd floor lounge balcony. The steel supports and metal decking are in place; the concrete pour for the floor is scheduled for later this week. The window framing and glass for the window curtain … Continue reading

Posted in Uncategorized | 1 Comment

February 5, 2011

With the scaffolding in place up in the clerestory area, we were able to climb up and get a first hand look from the inside out. The glass has been installed in 3 of the 4 sides – we’ll get … Continue reading

Posted in Uncategorized | 1 Comment

February 2, 2011

More materials delivered this week, including sheetrock and window panes. They have started to install the windows in the clerestory. Most of the studio walls have been sheetrocked and plaster skim coated, with painting soon to follow.The wood framing has … Continue reading

Posted in Uncategorized | Leave a comment