January 21, 2011

We had material deliveries earlier this week – for the clerestory, and also sheetrock and plaster for the interior walls. The front of the building was enclosed to create a warm dry space for building the new 2nd floor balcony. … Continue reading

Posted in Uncategorized | Leave a comment

January 12, 2011

We have new walls for the office and kiln room on the 1st floor. The extensive ductwork for heating and AC is being put in place on the 1st and 2nd floors. New scaffolding has been installed on the 2nd … Continue reading

Posted in Uncategorized | Leave a comment

January 4, 2011

Happy New Year and welcome back after the holiday break! I’m just back from our weekly project team meeting and all kinds of exciting things are happening. NSTAR, our electric company, arrived on site yesterday and delivered our 3 transformers. … Continue reading

Posted in Uncategorized | 2 Comments