Monthly Archives: November 2010
November 24, 2010
Concrete Day! – pouring the finish slab on the first floor. They poured the entryway on Monday, but today’s job is much bigger. Plus 4 days to dry and cure over the Thanksgiving break.
Posted in Uncategorized
Leave a comment
November 21, 2010
Many new developments this past week: The carpenters started laying down the supports for the new floor in one of the 2nd floor classrooms.They have nearly completed the 8 foot high walls for the studios and they put up the … Continue reading
Posted in Uncategorized
2 Comments
November 12, 2010
Time for a new roof! This past week they’ve been ripping up the old tar and gravel roof and laying down 6″ of insulation and a new rubber roof. They also need to stabilize the parapet around the roof, so … Continue reading
Posted in Uncategorized
Leave a comment
November 8, 2010
The new sprinkler system is being installed throughout the building, running pipes everywhere. More work on the new roof, plus putting up stud walls for the studios. The masons were in working on the new doorways to the classrooms on … Continue reading
Posted in Uncategorized
1 Comment
October 31, 2010
This past week was good weather for working on the roof. They’re up there stripping off the old tar and gravel and will lay down insulation and a new rubber roof. They also cut the opening for the clerestory and … Continue reading
Posted in Uncategorized
3 Comments