Lots of activity this week – Tony gave me the rundown: the plumbing inspector is due today for a rough inspection, we passed the compaction test (this refers to tamping down the dirt under the concrete slab), the grading is being completed, the surveyors did their inspection for the footings and piers (all right where they should be), the steel mesh for in the slab is being delivered today, the concrete comes on Friday (100 yards worth) for the 1st floor sub floor pour, and the steel delivery is scheduled for Monday. Yikes!

Finishing up the plumbing that goes under the slab floor

One area of dirt that has been compacted

The steel mesh arrives, right on time!

Advertisements
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s